試卷名稱 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-1
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-1》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The project manager is responsible for a system integration project. Which documents are required to perform quality assurance on the project ?
A、Quality metrics, work performance information, project management plan.
B、 Project management plan, lessons learned, scope statement.
C、 Cost performance baseline, project management plan, schedule performance index.
D、 Project management plan, variance analysis, risk register.