試卷名稱 信息系統(tǒng)項目管理師-pmp練習題-2
考試中心《信息系統(tǒng)項目管理師-pmp練習題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內容

Informed of a potential project changes, the project managers performed impact analysis. The project manager then submits the change request, and offers Change Control Board (CCB) to review and approval. CCB approved changes and grant implementation. Which one of the following should the project manager update first ?
A、Risk register.
B、 Project Charter.
C、 Project Management Plan.
D、 Quality management plan.