試卷名稱 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-3
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-3》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

During a meeting, a team member expresses concerns about the performance confidence of the newly developed component. During the stress testing of this components, the project manager notices that the components below the defined performance parameters. What should the project manager do next?
A、Request a corrective action to resolve this issue.
B、Utilize a checklist to limit the probability of failure.
C、Facilitate additional tests to continue examining the component.
D、Use a different tool to test the component thus conforming.