試卷名稱 信息系統(tǒng)項目管理師-pmp練習題-3
考試中心《信息系統(tǒng)項目管理師-pmp練習題-3》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A project to create a new product line includes three new products. Product number one and two will be released together, and developed in detail immediately. Product number three will be released within two years, and developed in more detail closer to the release date. The scope management plan is completed. Which of the following describes the project’s work breakdown structure (WBS)?
A、The WBS should not include product number three, as if will not be released until a later date.
B、 The WBS template from a previous project should be used to create the WBS for this project.
C、 The WBS should be created next, and it encompasses the full scope of project work.
D、 The WBS should be created with a technique called rolling wave planning.