試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(3)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(3)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

During the execution of the project, the customer reviews the project status with project manager. The customer realizes that expected work was not included in the statement of work.What is the next step the project management should take?
A、Submit the change request to the change control board for approval
B、Review the project schedule to accommodate the new request
C、Invoke the change request process
D、Perform fast tracking to exceed customer’s expectations